Work Profile Report [43W908]
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : शा0 सं0 3234/111(2)/21-13(एमएलए)/2017 टी0सी0-1 दि0 31.08.2021
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
76.10
Resanction Cost :
76.10
Tentative Cost :
55.00
Saving
21.10
Exp. Upto Last Fy :
40.97
For CFY 2024-2025
Remaining :
35.13
Demand :
13.00
Allotment :
13.00
Exp in CFY :
12.62
Total Up to Date Exp :
53.59
Work deferred
Sanction on : 3 years 3 months ago
31 Aug 2021
Physical Progress:
At start of FY 2024-2025 :
80 %
Up to Date :
98 %
Tentative Completion date on : 5 months 5 days from now
31 May 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Overall Saving 21.1 has been recorded as expected cost of work reduced from 76.1 to 55 . -- as on 17-Dec-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: