Work Profile Report [43W908]
Remarks
Tenders
Project Activities
alerts
Documents
Administrative Approval Detail : शा0 सं0 3234/111(2)/21-13(एमएलए)/2017 टी0सी0-1 दि0 31.08.2021
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
76.10
Resanction Cost :
76.10
Tentative Cost :
76.10
Exp. Upto Last Fy :
40.97
For CFY 2024-2025
Remaining :
35.13
Demand :
35.00
Allotment :
28.00
Exp in CFY :
7.00
Total Up to Date Exp :
47.97
Construction Started
Sanction on : 2 years 11 months ago
31 Aug 2021
Physical Progress:
At start of FY 2024-2025 :
80 %
Up to Date :
98 %
Tentative Completion date on : 7 months 2 weeks from now
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
किमी0 3 में 50 मी0 भाग पर विवाद होने के कारण कार्य अवरूद्ध है। -- as on 09-May-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: