Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 2.500 | 0.5 | 0.500 | 0.000 |
43W918 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0 सं0 6020/111(2)/21-12(एमएलए)/2017 टी0सी0-5 दि0 14.12.2021
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
82.23
Resanction Cost :
82.23
Tentative Cost :
82.23
Exp. Upto Last Fy : 45.02
For CFY 2024-2025
Remaining : 37.21
Demand : 37.22
Allotment : 0.00
Exp in CFY : 9.09
Total Up to Date Exp : 54.11
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 95 %
Sanction on :
2 years 7 months ago
14 Dec 2021
Tentative Completion date:
3 months 1 week from now
31 Oct 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
3 किमी0 में पहाड कटान कार्य पूर्ण। शेष कार्य प्रगति पर । -- as on 12-Jul-2024
Physical Peramenters