Administrative Approval Detail : शा0 सं0 5305/(1)111(2)/एमएलए/ 2017/टी0सी0- 111 दि0 1.11.2021
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
29.28
Resanction Cost :
29.28
Tentative Cost :
29.28
Exp. Upto Last Fy :
15.02
For CFY 2025-2026
Remaining :
14.26
Demand :
1.40
Allotment :
1.40
Exp in CFY :
1.40
Total Up to Date Exp :
16.42
Phase1 DPR Submitted
Sanction on : 4 years 2 months ago
01 Nov 2021
Physical Progress:
At start of FY 2025-2026 :
10 %
Up to Date :
10 %
Tentative Completion date on : 9 months 4 weeks from now
31 Oct 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
द्वितीय चरण स्वीकृति प्राप्त, प्रतिकर पत्रावली गठित कर अग्रिम कार्यवाही की जा रही है -- as on 23-Apr-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: