Work Profile Report [43W980]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : प्रमुख अभि0 का पत्रांक 895/07याता- पी0एम0जी0एस0वाई0-नि0/3 दि0 16.05.2023
TS Amount (lakhs) : 84.94 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
84.94
Resanction Cost :
84.94
Tentative Cost :
80.58
Saving
4.36
Exp. Upto Last Fy :
16.30
For CFY 2024-2025
Remaining :
68.64
Demand :
68.64
Allotment :
68.64
Exp in CFY :
51.06
Total Up to Date Exp :
67.36
Work completed
Sanction on : 1 year 7 months ago
16 May 2023
Physical Progress:
At start of FY 2024-2025 :
100 %
Up to Date :
100 %
Tentative Completion date on : 8 months 3 weeks ago
31 Mar 2024
Actual Completion Date : 7 months 12 hours ago
25 May 2024
Physical Linear Components
Remark
Overall Saving 4.36 has been recorded as expected cost of work reduced from 84.94 to 80.58 . -- as on 11-Dec-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: