Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4.5 | 4.5 | 4.500 | 0 | 0.000 | 0.000 |
43W988 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : e file no 48456 dt 21-08-2023
TS Amount (lakhs) : 104.13 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
104.13
Resanction Cost :
104.13
Tentative Cost :
104.13
Exp. Upto Last Fy : 66.83
For CFY 2024-2025
Remaining : 37.30
Demand : 37.30
Allotment : 0.00
Exp in CFY : 27.02
Total Up to Date Exp : 93.85
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
10 months 3 weeks ago
21 Aug 2023
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण । -- as on 15-Jun-2024
Physical Peramenters