Work Profile Report [43W989]
Tenders
Project Activities
alerts
Administrative Approval Detail : प्रमुख अभि0 का प0 सं0 1987/54 बजट (मार्ग/सेतुअनुरक्षण-सड़क सुरक्षा)/2023-24 दि0 10.08.2023
TS Amount (lakhs) : 1171.39 Lacs
Budget Financial Head : Not Available
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
1171.39
Resanction Cost :
1171.39
Tentative Cost :
1171.39
Exp. Upto Last Fy :
1,138.45
For CFY 2025-2026
Remaining :
32.94
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
1,138.45
Work completed
Sanction on : 1 year 10 months ago
10 Aug 2023
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 9 months 3 days ago
30 Sep 2024
Actual Completion Date : 3 months 2 days ago
31 Mar 2025
Physical Linear Components
Remark
कार्य पूर्ण। -- as on 16-Apr-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand