Work Profile Report [44W621]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शासनादेश संख्या 501/।।।(2)/22-11 (एम0एल0ए0)/2017 टीसी-5 दिंनाक 07 जनवरी, 2022
TS Amount (lakhs) : 380.56 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
380.56
Resanction Cost :
380.56
Tentative Cost :
380.56
Exp. Upto Last Fy :
352.28
For CFY 2024-2025
Remaining :
28.28
Demand :
5.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
352.28
In Maintenance After Completion
Sanction on : 2 years 11 months ago
07 Jan 2022
Physical Progress:
At start of FY 2024-2025 :
100 %
Up to Date :
100 %
Tentative Completion date on : 1 year 3 days ago
22 Dec 2023
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। दायित्व शेष। -- as on 16-May-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: