Work Profile Report [44W628]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शासनादेश संख्या-पत्रावली संख्या-22182 लोक निर्माण विभाग अनुभाग-2 देहरादून दिनंाक 29 अगस्त, 2022
TS Amount (lakhs) : 432.12 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
432.12
Resanction Cost :
432.12
Tentative Cost :
432.12
Exp. Upto Last Fy :
372.76
For CFY 2024-2025
Remaining :
59.36
Demand :
59.36
Allotment :
59.36
Exp in CFY :
59.36
Total Up to Date Exp :
432.11
Work completed
Sanction on : 2 years 3 months ago
29 Aug 2022
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
100 %
Tentative Completion date on : 7 months 4 weeks ago
27 Apr 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
work Completed. -- as on 02-Nov-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: