Work Profile Report [44W664]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : प्रमुख अभियन्ता (विभागाध्यक्ष) लोक निर्माण विभाग उत्तराखण्ड, देहरादून के पत्रांक 895/07 याता0-पी0एम0जी0एस0वाई0-नि0 ।।। दिनांक 16.05.2023
TS Amount (lakhs) : 217.58 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
217.58
Resanction Cost :
217.58
Tentative Cost :
217.02
Saving
0.56
Exp. Upto Last Fy :
208.12
For CFY 2024-2025
Remaining :
9.46
Demand :
9.46
Allotment :
6.40
Exp in CFY :
6.40
Total Up to Date Exp :
214.52
Work completed
Sanction on : 1 year 7 months ago
16 May 2023
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
100 %
Tentative Completion date on : 9 months 2 days ago
23 Mar 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Overall Saving 0.56 has been recorded as expected cost of work reduced from 217.58 to 217.02 . -- as on 10-Dec-2024