Work Profile Report [44W697]
Tenders
Project Activities
alerts
Documents
Administrative Approval Detail : ई पत्रावली संख्या-22183 लोक निर्माण अनुभाग-2 देहरादून दिनांक 07 अगस्त, 2023
TS Amount (lakhs) : 304.02 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
304.02
Resanction Cost :
304.02
Tentative Cost :
304.02
Exp. Upto Last Fy :
0.00
For CFY 2024-2025
Remaining :
304.02
Demand :
250.00
Allotment :
100.00
Exp in CFY :
103.60
Total Up to Date Exp :
103.60
Construction Started
Sanction on : 1 year 1 week ago
07 Aug 2023
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
10 %
Tentative Completion date on : 9 months 3 weeks from now
13 Jun 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
जी0-1 का कार्य पूर्ण । जी0-2 का कार्य प्रगति पर है। -- as on 05-Aug-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: