Work Profile Report [44W698]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : ई पत्राली संख्या-38165 लोक निर्माण अनुभाग-2 देहरादून दिनांक 04 अक्टूबर, 2023
TS Amount (lakhs) : 156.42 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
156.42
Resanction Cost :
156.42
Tentative Cost :
156.42
Exp. Upto Last Fy :
29.63
For CFY 2024-2025
Remaining :
126.79
Demand :
100.00
Allotment :
50.00
Exp in CFY :
33.80
Total Up to Date Exp :
63.43
Construction Started
Sanction on : 11 months 2 weeks ago
04 Oct 2023
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
20 %
Tentative Completion date on : 1 month 2 weeks from now
06 Nov 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
2.00 कि0मी0 लं0 में इन्टर कोट का कार्य पूर्ण। शेष लं0 में कार्य प्रगति पर। -- as on 01-Jul-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand