Work Profile Report [44W701]
Tenders
Aggrements
Project Activities
alerts
Samples
Administrative Approval Detail : शा0सं0- 3930/111(2)/09-08(एम0एल0ए0)/08 टी0सी0 दिनांक 02.03.2009
TS Amount (lakhs) : 105 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
105.00
Resanction Cost :
105.00
Tentative Cost :
105.00
Exp. Upto Last Fy :
63.57
For CFY 2024-2025
Remaining :
41.43
Demand :
28.78
Allotment :
27.54
Exp in CFY :
16.28
Total Up to Date Exp :
79.85
Construction Started
Sanction on : 15 years 9 months ago
02 Mar 2009
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
80 %
Tentative Completion date on :
Yet To Decide
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
0.50 कि0मी0 ल0 में पहाड कटान का कार्य पूर्ण। शेष लं0 में कार्य प्रगति पर। -- as on 06-Jun-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: