Work Profile Report [44W714]
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : ई पत्रावली संख्या-22183 लोक निर्माण अनुभाग-2 देहरादून दिनांक 05 जुलाई, 2024
TS Amount (lakhs) : 77.34 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
77.34
Resanction Cost :
77.34
Tentative Cost :
77.34
Exp. Upto Last Fy :
0.00
For CFY 2024-2025
Remaining :
77.34
Demand :
60.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.00
Construction Started
Sanction on : 4 months 2 weeks ago
05 Jul 2024
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
0 %
Tentative Completion date on : 6 months 2 weeks from now
11 Jun 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति पर। -- as on 25-Oct-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand