Work Profile Report : 44W733
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : ई पत्रावली संख्या-62704/11 लोक निर्माण अनुभाग-2 देहरादून दिनांक 14 फरवरी, 2025
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
151.44
Resanction Cost :
151.44
Tentative Cost :
151.44
Exp. Upto Last Fy :
0.00
For CFY 2025-2026
Remaining :
151.44
Demand :
55.00
Allotment :
54.03
Exp in CFY :
54.03
Total Up to Date Exp :
54.03
Construction Started
Sanction on : 11 months 4 weeks ago
14 Feb 2025
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
25 %
Tentative Completion date on : 2 months 1 day from now
14 Apr 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
4.00 कि0मी0 ल0 में से 2.00 किमी0 लम्बाई में पहाड़ कटान का कार्य पूर्ण। अवशेष प्रगति में। -- as on 02-Feb-2026
Assets :
Work not linked with IM
Bridges on The Basis of AI: