Work Profile Report [45W104]

मा0 मुख्यमंत्री जी की घोषणा संख्या-404/2013 के अन्तर्गत जगदीशिला (हिन्दाव) मोटर मार्ग का नव निर्माण कार्य।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

Administrative Approval Detail : शा0सं 6667/।।।(2)/13-32(प्रा0आ0)/2013 दिनांक 02.11.2013

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

43.13

Resanction Cost :

43.13

Tentative Cost :

43.13

Exp. Upto Last Fy :

41.78

For CFY 2024-2025

Remaining :

1.35

Demand :

1.35

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

41.78

Work completed

Sanction on : 10 years 8 months ago

22 Nov 2013

Physical Progress:

At start of FY 2024-2025 :

100 %

Up to Date :

100 %

Tentative Completion date on :

Yet To Decide

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
4
4
0.000
4
0.000
0.000

Remark

view all

मोटर मार्ग के द्वितीय चरण की स्वीकृति के सापेक्ष 4.00 कि0मी0 लम्बाई में मोटर मार्ग का निर्माण कार्य पूर्ण। उक्त स्वीकृति के सापेक्ष मुआवजा वितरण की कार्यवाही गतिमान। -- as on 01-May-2024

Rating : 100

Forest Case Pending At : 01: Withdraw

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: