Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 0.000 | 3 | 0.000 | 0.000 |
No of Bridges | 1 | 1 | 0 | 1 | 0 | 0 |
Span of Bridges [m] | 72 | 72 | 0.000 | 72 | 0.000 | 0.000 |
45W124 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश संख्या-4520/।।। (2)/15-08 (मु0 म0 घो0)/2015, दिनांक-19.06.2015।
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
21.40
Resanction Cost :
21.40
Tentative Cost :
21.40
Exp. Upto Last Fy : 2.64
For CFY 2024-2025
Remaining : 18.76
Demand : 18.76
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 2.64
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
9 years 4 weeks ago
19 Jun 2015
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
मोटर मार्ग पर द्वितीय चरण स्टेज-। के सापेक्ष 1.4 कि0मी0 लम्बाई पर पहाड़ कटान का कार्य पूर्ण। प्रथम चरण की स्वीकृति के सापेक्ष मुआवजा वितरण की कार्यवाही गतिमान। -- as on 02-May-2024
Physical Peramenters