Work Profile Report [45W17]

मूलगढ़-ठेला-गण्डराखाल मोटर मार्ग का भेलगढ़ी से पांडवगांव तक विस्तार कार्य।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

  • Documents
  • Samples

Administrative Approval Detail : शासनादेश संख्या-2171/।।। (2)/16-09 (एम0एल0ए0)/2015, दिनांक-19.07.2016।

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

29.34

Resanction Cost :

29.34

Tentative Cost :

29.34

Exp. Upto Last Fy :

6.18

For CFY 2025-2026

Remaining :

23.16

Demand :

0.00

Allotment :

0.32

Exp in CFY :

0.00

Total Up to Date Exp :

6.18

Survey work done

Sanction on : 9 years 5 months ago

19 Jul 2016

Physical Progress:

At start of FY 2025-2026 :

20 %

Up to Date :

20 %

Tentative Completion date on : 11 months 4 weeks from now

31 Dec 2026

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
9.5
9.5
0.000
9.5
0.000
0.000

Remark

view all

उक्त स्वीेकृति के सापेक्ष मुआवजा वितरित किया जाना है। -- as on 30-Dec-2025

Rating : 23

Forest Case Pending At : 17: AIP Govt of India

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: