Work Profile Report : 45W190
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0-2139(1)/।।।(2)/20-09(एम0एल0ए0)/2017 टी0सी0आई0, दि0 27.11.2020
TS Amount (lakhs) : 286.81 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
286.81
Resanction Cost :
286.81
Tentative Cost :
286.80
Saving
0.01
Exp. Upto Last Fy :
286.80
For CFY 2025-2026
Remaining :
0.01
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
286.80
In Maintenance After Completion
Sanction on : 5 years 3 months ago
27 Nov 2020
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 3 years 4 months ago
18 Oct 2022
Actual Completion Date : 3 years 4 months ago
18 Oct 2022
Physical Linear Components
Remark
Overall Saving 0.01 has been recorded as expected cost of work reduced from 286.81 to 286.80 . -- as on 30-Dec-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: