Work Profile Report [45W238]

राज्य योजना के अन्तर्गत कोन्ती-बणगांव-सिलोलीसेरा-चिलियालगांव तक मोटर मार्ग का निर्माण कार्य।(द्वितीय चरण स्टेज-।)
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

  • Aggrements
  • Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : शासन की ई0 पत्रावली सं0-37103,दि0-09.11.2022

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

92.88

Resanction Cost :

92.88

Tentative Cost :

92.88

Exp. Upto Last Fy :

85.65

For CFY 2024-2025

Remaining :

7.23

Demand :

7.23

Allotment :

7.23

Exp in CFY :

3.40

Total Up to Date Exp :

89.04

Work completed

Sanction on : 2 years 1 month ago

09 Nov 2022

Physical Progress:

At start of FY 2024-2025 :

79 %

Up to Date :

100 %

Tentative Completion date on : 8 months 3 weeks ago

31 Mar 2024

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
3.15
3.15
3.150
0
0.000
0.000

Remark

view all

पहाड़ कटान का कार्य पूर्ण। ग्रामीणों के क्षतिग्रस्त रास्तों व पाईप लाईन का कार्य किया जा रहा है। -- as on 06-Nov-2024

Rating : 100

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: