Work Profile Report [45W240]
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : शासन की ई0 पत्रावली सं0-37103,दि0-09.11.2022
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : Not Available
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
61.71
Resanction Cost :
61.71
Tentative Cost :
61.71
Exp. Upto Last Fy :
61.71
For CFY 2025-2026
Remaining :
0.00
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
61.71
Work completed
Sanction on : 2 years 7 months ago
09 Nov 2022
Physical Progress:
At start of FY 2025-2026 :
98 %
Up to Date :
100 %
Tentative Completion date on : 6 months 5 days ago
31 Dec 2024
Actual Completion Date : 6 months 5 days ago
31 Dec 2024
Physical Linear Components
Remark
work completed. -- as on 03-Apr-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: