Work Profile Report [45W26]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा.सं. 2503/ (1) 2/06 -37 (प्रा0आ0)/ 06 दि0 20.9.06
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
194.40
Resanction Cost :
194.40
Tentative Cost :
194.40
Exp. Upto Last Fy :
194.39
For CFY 2025-2026
Remaining :
0.01
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
194.39
In Maintenance After Completion
Sanction on : 18 years 9 months ago
20 Sep 2006
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 1 year 3 months ago
20 Mar 2024
Actual Completion Date : 1 year 3 months ago
31 Mar 2024
Physical Linear Components
Remark
WORK COMPLETED -- as on 22-Apr-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: