Work Profile Report [45W310]
Remarks
Tenders
Project Activities
alerts
Documents
Administrative Approval Detail : ई0 पत्रावली सं0-49198,दि0-18.05.2023
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
8.23
Resanction Cost :
8.23
Tentative Cost :
8.23
Exp. Upto Last Fy :
6.20
For CFY 2024-2025
Remaining :
2.03
Demand :
2.03
Allotment :
2.03
Exp in CFY :
0.00
Total Up to Date Exp :
6.20
none
Sanction on : 1 year 2 months ago
18 May 2023
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
40 %
Tentative Completion date on : 1 month 1 week from now
30 Sep 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Geotechnical investigation completed. Structural design in progress. -- as on 13-Jul-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: