Work Profile Report [45W315]
Tenders
Project Activities
Samples
Administrative Approval Detail : शासन की ई पत्रावली सं0-33957, 160134/2023, दिनांक-10.10.2023
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
405.99
Resanction Cost :
405.99
Tentative Cost :
405.99
Exp. Upto Last Fy :
58.72
For CFY 2024-2025
Remaining :
347.27
Demand :
336.00
Allotment :
236.48
Exp in CFY :
237.46
Total Up to Date Exp :
296.17
Construction Started
Sanction on : 1 year 1 month ago
10 Oct 2023
Physical Progress:
At start of FY 2024-2025 :
15 %
Up to Date :
80 %
Tentative Completion date on : 4 months 5 days from now
29 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
PC work completed in 4 km, remaining work in progress. -- as on 13-Nov-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand