Work Profile Report [45W315]
Tenders
Project Activities
Samples
Administrative Approval Detail : शासन की ई पत्रावली सं0-33957, 160134/2023, दिनांक-10.10.2023
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
405.99
Resanction Cost :
405.99
Tentative Cost :
405.99
Exp. Upto Last Fy :
58.72
For CFY 2024-2025
Remaining :
347.27
Demand :
336.00
Allotment :
299.19
Exp in CFY :
299.18
Total Up to Date Exp :
357.90
Construction Started
Sanction on : 1 year 2 months ago
10 Oct 2023
Physical Progress:
At start of FY 2024-2025 :
15 %
Up to Date :
90 %
Tentative Completion date on : 3 months 3 days from now
29 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
PC work completed in 5 km, remaining work in progress. -- as on 03-Dec-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: