Work Profile Report [45W315]
Tenders
Project Activities
alerts
Documents
Administrative Approval Detail : शासन की ई पत्रावली सं0-33957, 160134/2023, दिनांक-10.10.2023
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
405.99
Resanction Cost :
405.99
Tentative Cost :
405.99
Exp. Upto Last Fy :
58.72
For CFY 2024-2025
Remaining :
347.27
Demand :
335.82
Allotment :
108.65
Exp in CFY :
108.65
Total Up to Date Exp :
167.37
Construction Started
Sanction on : 10 months 6 days ago
10 Oct 2023
Physical Progress:
At start of FY 2024-2025 :
15 %
Up to Date :
45 %
Tentative Completion date on : 7 months 1 week from now
29 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Hill side cutting for Extra widening ,scupper, Walling and G1 and G2 work completed in 5 km length, G3 and other work in progress. -- as on 31-Jul-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: