Work Profile Report [45W319]

राज्य योजना केे अन्तर्गत आर्स से नैैक्वाडा-श्रीकोटगांव तक मोटर मार्ग का नवनिर्माण कार्य।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : ई0 पत्रावली सं0-37103,73397/2023,दि0-06.12.2023

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

14.25

Resanction Cost :

14.25

Tentative Cost :

0.10

Saving

14.15

Exp. Upto Last Fy :

0.10

For CFY 2025-2026

Remaining :

14.15

Demand :

0.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

0.10

Work deferred

Sanction on : 2 years 1 month ago

06 Dec 2023

Physical Progress:

At start of FY 2025-2026 :

10 %

Up to Date :

10 %

Tentative Completion date on : 2 months 6 days from now

31 Mar 2026

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
9.5
9.5
0.000
9.5
0.000
0.000

Remark

view all

वर्ष 2025 में पी0एम0जी0एस0वाई0 IV में चयनित हो गया है।निरस्तीकरण प्रस्ताव इस कार्यालय के प0-68/01सी0,दि0-07.01.2026 द्वारा कार्यालय अधीक्षण अभियन्ता, 8वाॅ वृत्त लो0नि0वि0 नई टिहरी को प्रेषित। -- as on 09-Jan-2026

Rating : 22

No Forest Case in The Work

Hindrance / Bottleneck : To Cancel

Assets :

Work not linked with IM

Bridges on The Basis of AI: