Work Profile Report [45W323]
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : पत्रावली संख्या- 48510/09, दिनांक-01.02.2024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
50.38
Resanction Cost :
50.38
Tentative Cost :
50.38
Exp. Upto Last Fy :
10.33
For CFY 2024-2025
Remaining :
40.05
Demand :
40.05
Allotment :
40.05
Exp in CFY :
25.72
Total Up to Date Exp :
36.04
Construction Started
Sanction on : 9 months 3 weeks ago
01 Feb 2024
Physical Progress:
At start of FY 2024-2025 :
20 %
Up to Date :
75 %
Tentative Completion date on :
Yet To Decide
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Hill side cutting work completed in 1 Km length. Protection work in progress. -- as on 13-Jul-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: