Work Profile Report [45W338]
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : ई0-पत्रावली संख्या-68022/09, 188763/2024, दिनांक- 08.02.2024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
153.63
Resanction Cost :
153.63
Tentative Cost :
130.00
Saving
23.63
Exp. Upto Last Fy :
0.09
For CFY 2024-2025
Remaining :
153.54
Demand :
130.00
Allotment :
61.40
Exp in CFY :
61.40
Total Up to Date Exp :
61.50
Construction Started
Sanction on : 10 months 2 weeks ago
08 Feb 2024
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
50 %
Tentative Completion date on : 8 months 1 week from now
04 Sep 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Overall Saving 23.63 has been recorded as expected cost of work reduced from 153.63 to 130 . -- as on 06-Dec-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand