Work Profile Report [45W57]

आली-मुण्डेती-शक्तिनगर (ग्यारहगांव) मोटर मार्ग का निर्माण कार्य । (प्रथम चरण लम्बाई-3.00)
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

  • Documents
  • Samples

Administrative Approval Detail : शा0सं0- 2387/।।।(2)/16-09(एम0एल0ए0)/2016, दिनांक- 01.09.2016

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

10.88

Resanction Cost :

10.88

Tentative Cost :

10.88

Exp. Upto Last Fy :

1.20

For CFY 2025-2026

Remaining :

9.68

Demand :

3.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

1.20

Phase1 DPR Submitted

Sanction on : 9 years 4 months ago

01 Sep 2016

Physical Progress:

At start of FY 2025-2026 :

15 %

Up to Date :

15 %

Tentative Completion date on : 1 year 2 months from now

31 Mar 2027

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
3
3
0.000
3
0.000
0.000

Remark

view all

मुआवजा पत्रावली गठित की जा रही है।द्वितीय चरण स्टेज-। की डी0पी0आर0 शासन स्तर पर। E-DPR ID-1757 -- as on 01-Jan-2026

Rating : 15

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: