Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 7 | 7 | 7.000 | 0 | 0.000 | 0.000 |
45W65 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0- 2387/।।।(2)/16-09(एम0एल0ए0)/2016, दिनांक- 01.09.2016
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 29.93 Lacs
Resanction Cost : 29.93 Lacs
Exp. Upto Last Fy : 0.35 Lacs
For CFY 2024-2025
Remaining : 29.58 Lacs
Demand : 0.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 0.35 Lacs
Survey work done
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
7 years 8 months ago
01 Sep 2016
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 02: Division
Bottelneck: no issue
इस मोटर मार्ग के पूर्व संरेखण केा प्रभागीय वनाधिकारी, टिहरी वन प्रभाग के पत्रांक संख्या-1505/12-1 नई टिहरी, दिनांक-14.12.2021 द्वारा निरस्त किया गया है। पुनः इस मोटर मार्ग के सिविल भूमि का हस्तान्तरण प्रस्ताव जिलाधिकारी, टिहरी गढवाल के पत्रांक संख्या-20/11-ए0एल0सी0-द्वितीय (2022-23) नई टिहरी, दिनांक-27.10.2023 द्वारा स्वीकृत किया गया है। तत्पश्चात दिनांक- 12.12.2023 को प्रभागीय वनाधिकारी, टिहरी वन प्रभाग द्वारा सिविल सोयम भूमि में अधिक वृक्ष आने के कारण इस प्रस्ताव को पुनः संशोधित कर स्वीकृति हेतु वन एवं पर्यावरण मंत्रालय को स्वीकृति हेतु प्रेषित करने के निर्देश दिये गये हैं, जिसके क्रम में इस प्रस्ताव को पुनः संशोधित किया जा रहा है। -- as on 20-Dec-2023
Physical Peramenters