Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 0.000 | 5 | 0.000 | 0.000 |
No of Bridges | 1 | 1 | 0 | 1 | 0 | 0 |
Span of Bridges [m] | 100 | 100 | 0.000 | 100 | 0.000 | 0.000 |
45W99 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं 6667/।।।(2)/13-32(प्रा0आ0)/2013 दिनांक 22.11.2013
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 39.25 Lacs
Resanction Cost : 39.25 Lacs
Exp. Upto Last Fy : 39.25 Lacs
For CFY 2024-2025
Remaining : 0.00 Lacs
Demand : 0.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 39.25 Lacs
Survey work done
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
10 years 5 months ago
22 Nov 2013
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 04: DFO
Bottelneck: no issue
वनभूमि के क्षेत्रफल में डम्पिंग ऐरिया का क्षेत्र शामिल न होने के कारण उक्त प्रस्ताव अपर प्रमुख वनसंक्षक एवं नोडल अधिकारी वन संरक्षण, देहरादून के पत्रांक संख्या- 2569/FP/UK/ROAD/14659/2015, दिनांक-03 जून, 2020 द्वारा आपत्तियों में वापस । प्रस्ताव WITHDRAW कर दिया गया है। पुनः नये सिरे से प्रस्ताव गठित कर आॅनलाईन कर दिया गया है। प्रभागीय वनाधिकारी वन प्रभाग, नई टिहरी द्वारा प्रकरण पर आपत्तियाॅ लगाई गई है।वर्तमान में यह मार्ग ब्रिडकुल को हस्तांतरित कर दिया गया है तथा वनभूमि हस्तान्तरण प्रस्ताव गठित कर इस कार्यालय के पत्रांक-1369/10 एम0जी0, दि0-16.09.2023 द्वारा प्रभागीय वनाधिकारी, टिहरी वन प्रभाग, नई टिहरी को प्रेषित कर दिया गया है। वर्तमान में प्रकरण वन संरक्षक स्तर पर प्रक्रियाधीन है। -- as on 20-Dec-2023
Physical Peramenters