Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.37 | 1.37 | 1.200 | 0.17 | 0.170 | 0.000 |
46W576 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई पत्रावली संख्या-33519 दिनांक 20 मार्च 2023
TS Amount (lakhs) : 39.48 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
39.48
Resanction Cost :
39.48
Tentative Cost :
39.48
Exp. Upto Last Fy : 37.05
For CFY 2024-2025
Remaining : 2.43
Demand : 21.37
Allotment : 0.00
Exp in CFY : 1.43
Total Up to Date Exp : 38.48
Construction Started
Physical Progress:
At start of FY 2024-2025 : 70 %
Up to Date : 70 %
Sanction on :
1 year 3 months ago
20 Mar 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर है। -- as on 14-Mar-2024
Physical Peramenters