Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.75 | 2.75 | 2.75 | 0 |
46W591 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई पत्रावली संख्या-33519 लोक निर्माण अनुभाग-2 देहरादून दिनांक 19 जुलाई 2023
TS Amount (lakhs) : 98.2 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
98.20
Resanction Cost :
98.20
Tentative Cost :
98.20
Exp. Upto Last Fy : 0.34
For CFY 2024-2025
Remaining : 97.86
Demand : 30.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.34
Unstarted Work
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
11 months 4 weeks ago
19 Jul 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: Alignment Dispute
अनुबन्ध गठित ग्रामीणों द्वारा विवाद किया जा रहा है। -- as on 10-Apr-2024
Physical Peramenters