Work Profile Report [46W674]
Tenders
Project Activities
alerts
Documents
Administrative Approval Detail : उत्तराखण्ड शासन के पत्रांक-212ध्।।।(2)ध्2024-01 (प्रा0आ0)ध्2023 लोक निर्माण अनुभाग-2 देहरादून दिनांक 31 जनवरी, 2024
TS Amount (lakhs) : 451.84 Lacs
Budget Financial Head : सड़क सुरक्षा कार्य ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
451.84
Resanction Cost :
451.84
Tentative Cost :
451.84
Exp. Upto Last Fy :
228.86
For CFY 2024-2025
Remaining :
222.98
Demand :
222.98
Allotment :
222.98
Exp in CFY :
118.07
Total Up to Date Exp :
346.93
Work completed
Sanction on : 10 months 3 weeks ago
31 Jan 2024
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
100 %
Tentative Completion date on : 2 months 3 weeks ago
03 Oct 2024
Actual Completion Date : 2 months 3 weeks ago
03 Oct 2024
Physical Linear Components
Remark
क्रैश बैरियर का कार्य पूर्ण। दायित्व अवशेष। -- as on 03-Oct-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand