Work Profile Report [46W676]
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : उत्तराखण्ड शासन के ई पत्रावली संख्या- 33519/13 लोक निर्माण अनुभाग-2 देहरादून दिनांक 29 जनवरी, 2024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
118.29
Resanction Cost :
118.29
Tentative Cost :
118.29
Exp. Upto Last Fy :
0.00
For CFY 2024-2025
Remaining :
118.29
Demand :
113.20
Allotment :
111.20
Exp in CFY :
111.20
Total Up to Date Exp :
111.20
Work completed
Sanction on : 9 months 3 weeks ago
29 Jan 2024
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
100 %
Tentative Completion date on : 2 months 3 weeks ago
30 Aug 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। दायित्व अवशेष। -- as on 27-Aug-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: