Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3.825 | 3.825 | 0.000 | 3.825 | 3.825 | 0.000 |
46W681 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : उत्तराखण्ड शासन के ई पत्रावली संख्या- 51399/13 लोक निर्माण अनुभाग-2 देहरादून दिनांक 05 मार्च 2024
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
155.82
Resanction Cost :
155.82
Tentative Cost :
155.82
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 155.82
Demand : 20.00
Allotment : 0.00
Exp in CFY : 0.16
Total Up to Date Exp : 0.16
in Tendering Stage
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
4 months 1 week ago
05 Mar 2024
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
निविदा प्राप्त निस्तारण किया जा रहा है। -- as on 28-Jun-2024
Physical Peramenters