Work Profile Report [46W681]
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : उत्तराखण्ड शासन के ई पत्रावली संख्या- 51399/13 लोक निर्माण अनुभाग-2 देहरादून दिनांक 05 मार्च 2024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
155.82
Resanction Cost :
155.82
Tentative Cost :
155.82
Exp. Upto Last Fy :
0.00
For CFY 2024-2025
Remaining :
155.82
Demand :
146.82
Allotment :
46.20
Exp in CFY :
46.20
Total Up to Date Exp :
46.20
Construction Started
Sanction on : 8 months 2 weeks ago
05 Mar 2024
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
55 %
Tentative Completion date on :
Yet To Decide
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
द्वितीय चरण स्टेज-2 के कार्य प्रगति पर है। -- as on 28-Oct-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand