Work Profile Report [46W710]
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : उत्तराखण्ड शासन के ई पत्रावली संख्या-30972 लोक निर्माण अनुभाग-2 देहरादून दिनांक 23 अगस्त 2024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
162.22
Resanction Cost :
162.22
Tentative Cost :
162.22
Exp. Upto Last Fy :
101.50
For CFY 2025-2026
Remaining :
60.72
Demand :
55.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
101.50
Construction Started
Sanction on : 7 months 2 weeks ago
23 Aug 2024
Physical Progress:
At start of FY 2025-2026 :
0 %
Up to Date :
60 %
Tentative Completion date on : 2 months 1 week from now
15 Jun 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
जी0-3 का कार्य प्रगति पर है। -- as on 02-Apr-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand