Work Profile Report [47W136]
Tenders
Aggrements
Project Activities
alerts
Samples
Administrative Approval Detail : शा0सं0 3376/।।।(2)/12-27 (सामान्य)/2010 दि0 05.10.2012
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
88.20
Resanction Cost :
88.20
Tentative Cost :
88.20
Exp. Upto Last Fy :
21.64
For CFY 2024-2025
Remaining :
66.56
Demand :
15.00
Allotment :
0.10
Exp in CFY :
0.00
Total Up to Date Exp :
21.64
Phase1 DPR Submitted
Sanction on : 12 years 1 month ago
05 Oct 2012
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
90 %
Tentative Completion date on : 7 months 3 weeks ago
31 Mar 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
मार्ग की ड़ी0पी0आर0 शासन में वित्तीय एवं प्रशासनिक स्वीकृति हेतु लम्बित है। -- as on 05-Nov-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: