Work Profile Report [47W167]

खजरा बैंजवाड़ी मोटर मार्ग के कि0मी0 4 से आगे बरसीला पोथ मंजूली तक मोटर मार्ग का विस्तार। (प्रथम चरण के कार्य)
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

  • Documents
  • Samples

Administrative Approval Detail : श्शा0सं0 6970/।।।(2)/13-40(प्रा0आ0)/2013 दि0 14.12.2013

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

31.12

Resanction Cost :

31.12

Tentative Cost :

31.12

Exp. Upto Last Fy :

4.36

For CFY 2024-2025

Remaining :

26.76

Demand :

7.00

Allotment :

11.48

Exp in CFY :

11.48

Total Up to Date Exp :

15.84

Alignment Approved

Sanction on : 11 years 1 week ago

14 Dec 2013

Physical Progress:

At start of FY 2024-2025 :

0 %

Up to Date :

50 %

Tentative Completion date on : 3 months 5 days from now

31 Mar 2025

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
4
4
0.000
4
0.000
0.000

Remark

view all

प्रकरण उपजिलाधिकारी स्तर पर दाखिल खारिज हेतु लम्बित है। -- as on 24-Dec-2024

Rating : 53

Forest Case Pending At : 12: AIP DM

Hindrance / Bottleneck : Long Term Forest Approval

Assets :

Work not linked with IM

Bridges on The Basis of AI: