Work Profile Report [47W188]

चैण्डी से भदली, घटधार, थानकोट, घेरा होतु हुये ग्राम सिमलासू बैण्ड तक मोटर मार्ग का निर्माण।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

  • Documents
  • Samples

Administrative Approval Detail : शा0 सं0 549/।।।(2)/14-49(प्रा0आ0)/2013 दि0 29.01.2014

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

43.80

Resanction Cost :

43.80

Tentative Cost :

43.80

Exp. Upto Last Fy :

38.36

For CFY 2025-2026

Remaining :

5.44

Demand :

5.44

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

38.36

Alignment Approved

Sanction on : 11 years 2 months ago

29 Jan 2014

Physical Progress:

At start of FY 2025-2026 :

0 %

Up to Date :

90 %

Tentative Completion date on : 3 months 3 weeks from now

31 Jul 2025

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
6
5.27
0.000
5.27
5.270
0.000

Remark

view all

मार्ग की अनुपालन आख्या इस कार्यालय के पत्रांक-1681/33सी0 दिनांक 06.09.2024 द्वारा प्रभागीय वनाधिकारी टिहरी वन प्रभाग नई टिहरी को प्रेषित की गई थी। जिस पर उनके द्वारा अपने कार्यालय आदेश सं0-371/12-1 नई टिहरी दिनांक 18.10.2024 द्वारा कार्य प्रारम्भ करने की अनुमति प्रदान की गई है। -- as on 05-Nov-2024

Rating : 95

Forest Case Pending At : 13: AIP DFO

Hindrance / Bottleneck : Long Term Forest Approval