Work Profile Report [47W205]

Closed Work ढुण्डसिर शिवालय सम्पर्क मोटर मार्ग का नवनिर्माण।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : श्शा0 सं0 1144/।।।(2)/14-72(प्रा0आ0)/2013 दि0 04.03.2014

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : Not Available

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

11.67

Resanction Cost :

11.67

Tentative Cost :

11.67

Exp. Upto Last Fy :

11.67

For CFY 2025-2026

Remaining :

0.00

Demand :

0.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

11.67

Work completed

Sanction on : 11 years 4 months ago

04 Mar 2014

Physical Progress:

At start of FY 2025-2026 :

0 %

Up to Date :

100 %

Tentative Completion date on : 3 months 1 week ago

31 Mar 2025

Actual Completion Date : 3 months 3 weeks ago

15 Mar 2025

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
1.5
1.5
1.500
0
0.000
0.000

Remark

view all

वनभूमि हस्तान्तरण की विधिवत स्वीकृति प्राप्त। -- as on 24-Dec-2024

Rating : 100

Forest Case Pending At : 18: Final Approval

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: