Work Profile Report [47W206]

जामणीखाल से चैड़ियों से वालगुरू से भैंसकोट तक मोटर मार्ग का नवनिर्माण कार्य
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

  • Documents
  • Samples

Administrative Approval Detail : श्शा0 सं0 1144/।।।(2)/14-72(प्रा0आ0)/2013 दि0 04.03.2014

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

62.24

Resanction Cost :

62.24

Tentative Cost :

62.24

Exp. Upto Last Fy :

11.26

For CFY 2024-2025

Remaining :

50.98

Demand :

10.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

11.26

Alignment Approved

Sanction on : 10 years 8 months ago

04 Mar 2014

Physical Progress:

At start of FY 2024-2025 :

0 %

Up to Date :

20 %

Tentative Completion date on : 4 months 1 week from now

31 Mar 2025

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
8
4.5
0.000
4.5
4.500
0.000

Remark

view all

अनुपालन आख्या सत्यापित करने हेतु इस कार्यालय के पत्रांक 1994/33सी0 दिनांक 23.10.2024 द्वारा अपर प्रमुख वन संरक्षक एवं नोड़ल अधिकारी को अनुस्मारक पत्र प्रेषित किया गया है। -- as on 23-Oct-2024

Rating : 21

Forest Case Pending At : 15: AIP Nodal

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: