Work Profile Report [47W25]
Tenders
Aggrements
Project Activities
alerts
Documents
Administrative Approval Detail : शा0स0 5108(।)/111-(2)/11-23 (प्रा0 आ0)/ 2009 दि0 26.09.2011
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
138.60
Resanction Cost :
138.60
Tentative Cost :
138.60
Exp. Upto Last Fy :
40.19
For CFY 2024-2025
Remaining :
98.41
Demand :
10.00
Allotment :
0.25
Exp in CFY :
0.25
Total Up to Date Exp :
40.44
Construction Started
Sanction on : 12 years 10 months ago
26 Sep 2011
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
35 %
Tentative Completion date on : 7 months 2 weeks from now
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
अपर पमुख वन संरक्षक एवं नोड़ल अधिकारी देहरादून द्वारा आॅन लाईन कम्प्लाईन्स दिनांक 24.02.2023 को सत्यापित की जा चुकी है। -- as on 14-Jul-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: