Work Profile Report [47W263]

क्वीली से मछियारी होते हुए नैखरी तक मोटर मार्ग का विस्तार कार्य।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

  • Documents
  • Samples

Administrative Approval Detail : 1152/।।।(2)/16-56(प्रा0आ0)/2015 टी0सी0 दि0 29.02.2016

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

42.80

Resanction Cost :

42.80

Tentative Cost :

42.80

Exp. Upto Last Fy :

20.55

For CFY 2025-2026

Remaining :

22.25

Demand :

22.25

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

20.55

Alignment Approved

Sanction on : 9 years 1 month ago

29 Feb 2016

Physical Progress:

At start of FY 2025-2026 :

0 %

Up to Date :

50 %

Tentative Completion date on : 3 months 3 weeks from now

31 Jul 2025

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
8
5
0.000
5
5.000
0.000

Remark

view all

प्रकरण विधिवत स्वीकृति हेतु भारत सरकार स्तर पर लम्बित है। -- as on 24-Dec-2024

Rating : 54

Forest Case Pending At : 17: AIP Govt of India

Hindrance / Bottleneck : Long Term Forest Approval

Assets :

Work not linked with IM

Bridges on The Basis of AI:

© PWD Uttarakhand