Work Profile Report [47W270]

पौड़ीखाल भासौं मिसिंग लिंक मोटर मार्ग का नव निर्माण (प्रथम चरण)
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

Administrative Approval Detail : श्शा0स0 1836/।।।(2)/18-10(एम.एल.ए.)/2016 दि0 13.07.2016

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

20.50

Resanction Cost :

20.50

Tentative Cost :

20.50

Exp. Upto Last Fy :

13.67

For CFY 2024-2025

Remaining :

6.83

Demand :

5.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

13.67

Construction Started

Sanction on : 8 years 1 month ago

13 Jul 2016

Physical Progress:

At start of FY 2024-2025 :

0 %

Up to Date :

10 %

Tentative Completion date on : 7 months 2 weeks from now

31 Mar 2025

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
2.5
2.12
2.12
-

Remark

view all

अनुपालन आख्या आॅन लाईन अपलोड़ की जा चुकी है। जिसे अपर प्रमुख वन संरक्षक एवं नोड़ल अधिकारी देहरादून द्वारा सत्यापित किया जाना है। 0 -- as on 15-Jul-2024

Rating : 78

Forest Case Pending At : 15: AIP Nodal

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: