Work Profile Report [47W272]

भ्वींट गधेरे से तुणगी-भटकोट मोटर मार्ग का नव निर्माण (प्रथम चरण)
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

  • Documents
  • Samples

Administrative Approval Detail : श्शा0स0 1836/।।।(2)/18-10(एम.एल.ए.)/2016 दि0 13.07.2016

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

37.80

Resanction Cost :

37.80

Tentative Cost :

37.80

Exp. Upto Last Fy :

1.01

For CFY 2024-2025

Remaining :

36.79

Demand :

5.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

1.01

Alignment Approved

Sanction on : 8 years 4 months ago

13 Jul 2016

Physical Progress:

At start of FY 2024-2025 :

0 %

Up to Date :

40 %

Tentative Completion date on : 4 months 1 week from now

31 Mar 2025

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
3.5
3.5
0.000
3.5
3.500
0.000

Remark

view all

भूमि की दरें अधिक होने के कारण स्वीकृत लागत के अन्तर्गत प्रतिकर वितरण सम्भव न होने के कारण प्रतिकर प्रस्ताव गठित कर मुख्य अभियंता पौडी को प्रेषित किया गया है। स्वीकृति के पश्चात प्रतिकर वितरित किया जायेगा। -- as on 21-Oct-2024

Rating : 44

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: