Work Profile Report [47W300]

वीरखाल से बरसीला होते हुये ग्राम पंचायत मंजुली तक मोटर मार्ग का निर्माण (प्रथम चरण)
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

  • Documents
  • Samples

Administrative Approval Detail : श्शा0सं0 2331/।।।(2)/16-10(एम.एल.ए.)/2016 दि0 17.08.2016

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

27.10

Resanction Cost :

27.10

Tentative Cost :

27.10

Exp. Upto Last Fy :

2.62

For CFY 2024-2025

Remaining :

24.48

Demand :

4.00

Allotment :

1.50

Exp in CFY :

1.42

Total Up to Date Exp :

4.03

Work completed

Sanction on : 8 years 3 months ago

17 Aug 2016

Physical Progress:

At start of FY 2024-2025 :

0 %

Up to Date :

100 %

Tentative Completion date on : 4 months 3 days from now

31 Mar 2025

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
5
4
0.000
4
0.000
0.000

Remark

view all

पहाड़ कटान का कार्य पूर्ण। मुआवजा वितरण की कार्यवाही गतिमान है। -- as on 05-Nov-2024

Rating : 109

Forest Case Pending At : 18: Final Approval

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI:

© PWD Uttarakhand