Work Profile Report [47W300]
Tenders
Aggrements
Project Activities
alerts
Samples
Administrative Approval Detail : श्शा0सं0 2331/।।।(2)/16-10(एम.एल.ए.)/2016 दि0 17.08.2016
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
27.10
Resanction Cost :
27.10
Tentative Cost :
27.10
Exp. Upto Last Fy :
2.62
For CFY 2024-2025
Remaining :
24.48
Demand :
4.00
Allotment :
1.50
Exp in CFY :
1.42
Total Up to Date Exp :
4.03
Work completed
Sanction on : 8 years 3 months ago
17 Aug 2016
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
100 %
Tentative Completion date on : 4 months 3 days from now
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
पहाड़ कटान का कार्य पूर्ण। मुआवजा वितरण की कार्यवाही गतिमान है। -- as on 05-Nov-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand