Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 5 | 0 |
47W302 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : श्शा0सं0 2331/।।।(2)/16-10(एम.एल.ए.)/2016 दि0 17.08.2016
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
24.60
Resanction Cost :
24.60
Tentative Cost :
24.60
Exp. Upto Last Fy : 1.90
For CFY 2024-2025
Remaining : 22.70
Demand : 4.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 1.90
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 40 %
Sanction on :
7 years 11 months ago
17 Aug 2016
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
द्वितीय चरण के अन्तर्गत पहाड़ कटान का कार्य प्रगति पर है। भूमि प्रतिकर गठित किया जा रहा है। -- as on 15-Jul-2024
Physical Peramenters