Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3.5 | 3.5 | 3.5 | 0 |
47W323 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश सं0 2224/।।।(2)/16-48 (प्रा0आ0)/2016 दि0 15.12.16
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 17.22 Lacs
Resanction Cost : 17.22 Lacs
Exp. Upto Last Fy : 0.32 Lacs
For CFY 2024-2025
Remaining : 16.90 Lacs
Demand : 2.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 0.32 Lacs
Alignment Approved
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
7 years 4 months ago
15 Dec 2016
Tentative Completion date:
1 month 1 week ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 03: DM
Bottelneck: no issue
भारत सरकार ने अपने पत्रांक-8बी0/यू0सी0पी0/06/01/2021/एफ0सी0/748 दिनांक 22.09.2021 द्वारा प्रस्ताव को ग्राम सिलगढ़ से आगे ले जाने का कोई औचित्य नहीं है की आपत्ति लगाई है, एवं इस मार्ग के पुनरीक्षित प्रस्ताव प्रेषित करने हेतु निर्देशित दिये गये है। -- as on 23-Dec-2023
Physical Peramenters