Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 8 | 8 | 8 | 0 |
47W33 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0स0 764/111-(2)/08-65 (प्रा0 आ0)/2007 दि0 24.03.08
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 280.00 Lacs
Resanction Cost : 280.00 Lacs
Exp. Upto Last Fy : 2.82 Lacs
For CFY 2024-2025
Remaining : 277.18 Lacs
Demand : 10.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 2.82 Lacs
Alignment Approved
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
16 years 1 month ago
24 Mar 2008
Tentative Completion date:
10 months 2 weeks from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 04: DFO
Bottelneck: no issue
क्षतिपूरक वृक्षारोपण की भूमि उपलब्ध हो चुकी है। वन भूमि हस्तान्तरण प्रस्ताव गठित। उपजिलाधिकारी समिति के हस्ताक्षर हो चुके है। प्रभागीय वनाधिकारी नरेन्द्रनगर वन प्रभाग को वन भूमि प्रस्ताव प्रेषित जांच हेतु प्रेषित । -- as on 10-Mar-2024
Physical Peramenters