Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 12 | 12 | 12 | 0 | ||
No of Bridges | 1 | 1 | 1 | 0 | ||
Span of Bridges [m] | 24 | 24 | 24 | 0 |
47W357 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश सं0 5221/।।।(2)/18-10(एम0एल0ए0)/2017 टी0सी0 दिनांक 23.10.2018
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
40.56
Resanction Cost :
40.56
Tentative Cost :
40.56
Exp. Upto Last Fy : 2.47
For CFY 2024-2025
Remaining : 38.09
Demand : 5.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 2.47
Alignment Approved
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
5 years 8 months ago
23 Oct 2018
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 04: DFO
Bottelneck: no issue
क्षतिपूरक वृक्षारोपण हेतु चयनित स्थल के मानचित्र प्रभागीय वनाधिकारी स्तर पर लम्बित है। 07- -- as on 15-Jul-2024
Physical Peramenters