Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4.5 | 4.5 | 4.5 | 0 |
47W377 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 2277/।।।(2)/19-10(एम0एल0ए0)/2017 टी0सी0 दिनांक 21.06.2019
TS Amount (lakhs) : 31.34 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
31.34
Resanction Cost :
31.34
Tentative Cost :
31.34
Exp. Upto Last Fy : 1.87
For CFY 2024-2025
Remaining : 29.47
Demand : 2.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 1.87
Alignment Approved
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 40 %
Sanction on :
5 years 3 weeks ago
21 Jun 2019
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 11: AIP Division
Bottelneck: no issue
Construction of Village Gehar motor road has been sanctioned for the Part-II stage-I Hill side cutting by the Govt of UK E-file no 39205 PW.D section-2 dated 12 march 2024. मार्ग पर एन0पी0वी0 की धनराशि प्राप्त नहीं हुई है। एन0पी0वी0 की धनराशि प्राप्त होने के उपरान्त एन0पी0वी0 की धनराशि कैम्पा फन्ड़ में जमा कर दी जायेगी। -- as on 15-Jul-2024
Physical Peramenters